These projects have been added to the plan based on a combination of factors, including community use and demand, the current condition of the assets, and their alignment with other planned capital projects, such as playground upgrades. Endorsement of this plan will result in the formal inclusion of these projects within both the Buildings Asset Management Plan and the LTFP, ensuring they are considered in future planning, funding, and delivery. This approach ensures that Council’s investment decisions are both responsive to community needs and strategically coordinated across multiple asset areas.

The delivery plan for new public toilet installations may be adjusted to align with the timing of broader strategic projects and infrastructure upgrades. Coordinating the installation of toilets with these projects allows for more efficient use of resources, minimises disruption, and ensures that facilities are delivered in locations and at times that best support community needs and long-term planning objectives. As such, some installations may be rescheduled to a different year than originally proposed to achieve better alignment and integration with wider initiatives.

Projects marked with an asterisk in the table below (*) are currently not included in the Buildings Asset Management Plan or the Long-Term Financial Plan (LTFP).
Costs are indicative.

  • Schedule of public toilet building works 2025/26

    Replace

    • Eric Sutton Reserve Toilets Refurbish
      $200,000
    • Semaphore Foreshore - (Opposite Paxton Street) Refurbish
      $110,000
    New
    • Accessible Toilet, Semaphore South (near Shelly’s kiosk)
      $300,000
    • Jack Watkins Toilet - New Construction
      $250,000
    Total yearly investment
    • $860,000
  • Schedule of public toilet building works 2026/27

    Replace

    • Glanville Golf Course Toilets - Refurbish
      $99,800

    New

    • The Parkway - New Construction
      $250,000
    • Birkenhead Reserve - New Construction
      $200,000
    • Peter Cousins Reserve - New Construction
      $227,500
    • Changing Places Facility - New Construction (Location to be confirmed)
      $300,000
    • Leopold Conrad Reserve - New Construction
      $250,000*

    Total yearly investment

    • $1,327,300
  • Schedule of public toilets building works 2027/28

    Replace

    • Osborne Foreshore Toilets (Moldavia) - Refurbish
      $80,000
    • Snowdens Beach Toilets - Refurbish
      $80,000*
    • Devon Park Reserve - Refurbish
      $40,000*

    New

    • Semaphore Lawn Tennis Club Toilet - New Construction
      $200,000
    • Changing Places Facility - New Construction (Location to be confirmed)
      $300,000
    • Ray Norton Reserve - New Construction
      $250,000
    • RB Connolly Reserve - New Construction
      $250,000
    • Somerset Reserve - New Construction
      $250,000*

    Total yearly investment
    $1,450,000

  • Schedule of Public Toilet building works 2028/29

    Replace

    • Beefacres Reserve - Refurbish
      $80,000*
    • North Haven Kiosk - Refurbish
      $80,000*

    New

    • Peter McKay Reserve - New Construction
      $220,000
    • Changing Places Facility - New Construction (Location to be confirmed)
      300,000
    • Yandra Reserve - New Construction
      $250,000

    Total yearly investment

    • $930,000
  • Schedule of Public Toilet building works 2029/30

    New

    • Hartley Grove Reserve - New Construction
      $250,000
    Total yearly investment
    • $250,000

    Note: Council has set aside a design and construction budget for a toilet within the port precinct in it’s Long Term Financial Plan and will include these works within the Capital Works Program when the timing of this project is known.
    $1,700,000

    Total program investment $6,517,300

Edit

Contact Us

Have questions or want to learn more about a project, contact us below:

Contact Information
Phone 08 8405 6600
Email consultation@cityofpae.sa.gov.au
Website www.cityofpae.sa.gov.au
Community Engagement

Contact information may be required to comply with Council’s Community Engagement Policy. All submissions will be treated as public documents upon receipt.

Closing the loop, we will make efforts to 'close-the-loop' with project contributors and followers. We may occasionally send information to acknowledge a contribution, provide key updates on engagement and project processes and outcomes.